Question: Problem Statement A 8 m high embankment is planned to level up a depressed ground for highway construction. The soll profile consists of 3 m
Problem Statement
A high embankment is planned to level up a depressed ground for highway construction. The soll profile consists of of silty sand, underlain by of clay, and followed by dense sand. An undisturbed sample was retrieved from the middle of the clay layer for the oedometer test Calculate a the expected settlement and b the time needed for of consolidation.
table of embankment fill: