Question: Problem#5 the critical path and calculate the ES, EF, LS and LF for the critical path. Activity 1-2 1-3 244 3-4 3-5 Name A B

Problem#5 the critical path and calculate the ES,
Problem#5 the critical path and calculate the ES, EF, LS and LF for the critical path. Activity 1-2 1-3 244 3-4 3-5 Name A B D E F Ti 4 1 1 1 Activity 5-6 5-7 6-8 7-8 8-10 9-10 Name G H 1 Time (day) 4 8 1 2 5 7 6 K L 5 Problem#5: Construct the activity network for the table given below also determine