Question: PROBLEMS: ANSWER # 2 The following problems are designed to assess your comprehension of the material conveyed above. Show all of your math / steps

PROBLEMS: ANSWER #2
The following problems are designed to assess your comprehension of the material conveyed above. Show all of your math/steps and solve the problems in the space provided below. All solutions shall be highlighted by placing them in a box (e.g. AND production rates must be expressed using four (4) decimal places.
Convert the output of 2,400 square feet of 3'' EPS insulation EIFS per 8 hour day for a five person crew to a production rate in man-hours per square foot.
dQUESTION 2: Based upon the prior problem and using the J-1 crew from the chart below, estimate the total bare labor cost to install 175,000 sf of 3'' EPS insulation.
PROBLEMS: ANSWER # 2 The following problems are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!