Question: PROBLEMS: Assume the following information. table [ [ Probability of failure,Consequences of failure ] , [ Maturity = , 0 . 4 7 ,

PROBLEMS:
Assume the following information.
\table[[Probability of failure,Consequences of failure],[Maturity=,0.47,Cost =,0.16],[Complexity =,0.25,Schedule =,0.61],[Dependancy =,0.64,Reliability =,0.2],[,,Performance,0.66]]
Calculate the overall risk factor and assess the level of risk for this project. (Method: Excel, Points: 10)
 PROBLEMS: Assume the following information. \table[[Probability of failure,Consequences of failure],[Maturity=,0.47,Cost =,0.16],[Complexity