Question: Problem-solving: The AON network is associated with the activities (A through I) for Carl Bettertons construction project. The AON network shows a sequence of activities
Problem-solving: The AON network is associated with the activities (A through I) for Carl Bettertons construction project. The AON network shows a sequence of activities and a task time (days) for each activity.
ActivityImmediate
predecessor(s)
TimeESEFLSLFSlackCritical?A9B7C3D6E9F4G6H5I3- What is the critical path?
- What is the project length?