Question: PROBS5 Case Studies Case Study 1 The following activities are part of a project to be scheduled using CPM. Immediate Predecessors Time in Weeks ACTIVITY

PROBS5 Case Studies Case Study 1 The following

PROBS5 Case Studies Case Study 1 The following activities are part of a project to be scheduled using CPM. Immediate Predecessors Time in Weeks ACTIVITY | B 1 F a. Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and insert arrows to show direction. 22 22 b. What is the critical Path? C. How many weeks will it take to complete the project? d. How much slack does Activity B have