Question: Process Analysis A three step process is followed to make sandwiches. Slice bread and place meat Add veggies and condiments Wrap and payment Processing Time
Process Analysis
A three step process is followed to make sandwiches.
| Slice bread and place meat | Add veggies and condiments | Wrap and payment | |
| Processing Time | 1 min | 3 min | 2 min |
| Workers | 1 | 2 | 1 |
What is the process flow rate if demand is 36 sandwiches per hour?
What is the utilization for each area?