Question: Process Analysis Multiple Flow Units The table below provides the daily demand rate and daily capacity for each stage in a lumber process with attrition.

Process Analysis Multiple Flow Units

The table below provides the daily demand rate and daily capacity for each stage in a lumber process with attrition.

Task Demand Rate Capacity
Accept order of lumber 120 200
Inspect lumber 120 180
Cut lumber into boards 100 140
Strap boards together and store 90 120

What is the implied utilization for each task?

Which task is the bottleneck?

Is this process demand constrained or resource constrained?