Question: process at your firm. Table 7.7 contacts the data you will need to conduct a cost analysis of the project. Indirect costs are $1,600 per

process at your firm. Table 7.7 contacts the data you will need to conduct a cost analysis of the project. Indirect costs are $1,600 per week, and a penalty costs are $1,200 per week after week 12. Activity Immediate P..(s)

Activity

Immediate P..(s)

Normal Time (wks)

Crash Time (wks)

Normal Cost $

Crash Cost

A

-

4

1

5,000

8,000

B

-

5

3

8,000

10,000

C

A

1

1

4,000

4,000

D

B

6

3

6,000

12,000

E

B,C

7

6

4,000

7,000

F

D

7

6

4,000

7,000

a. What is the minimum-cost schedule for this project? b. What is the difference in total project costs between the earliest completion time of the project using normal times and the minimum-cost schedule you derived in part (a)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!