Question: PROCESS CAPACITY CALCULATIONS ( keep your answers for the two following questions ) Parts go through the following process: Fabrication - . . - >
PROCESS CAPACITY CALCULATIONS keep your answers for the two following questions
Parts go through the following process:
Fabrication Paint Assembly Finished Goods
Capacity information is as follows:
Fabrication Department
Can produce partshour per machine
One hour shift
Six machines
Fiveday week
Paint Department
Can process partshour
Two hour shift
Fiveday week
Assembly Department
Can produce assemblieshour
One hour shift
Fourday week
What is the weekly capacity for each of the department?