Question: Process Flow for Making a Shirt Consider the following process flow diagram for making a shirt. All steps (A, B, C, D, and E) are
-
Process Flow for Making a Shirt
Consider the following process flow diagram for making a shirt. All steps (A, B, C, D, and E) are necessary to create each finished unit (shirt). Each step employs a single worker. Exact task times, in minutes/unit, are shown at each step. For example, it takes exactly 4 minutes to
Refer to the Process Flow Diagram for Making a Shirt. What is the minimum throughput time, that is, the fastest a rush order for one unit can go through the process?
a. 12 minutes
b. 26 minutes
c. 31 minutes
d. 36 minutes
e. None of the answers are correct.