Question: Process Flow for Making a Shirt Consider the following process flow diagram for making a shirt. All steps (A, B, C, D, and E) are

  1. Process Flow for Making a Shirt

    Consider the following process flow diagram for making a shirt. All steps (A, B, C, D, and E) are necessary to create each finished unit (shirt). Each step employs a single worker. Exact task times, in minutes/unit, are shown at each step. For example, it takes exactly 4 minutes to

    Refer to the Process Flow Diagram for Making a Shirt. What is the minimum throughput time, that is, the fastest a rush order for one unit can go through the process?

    a.

    12 minutes

    b.

    26 minutes

    c.

    31 minutes

    d.

    36 minutes

    e.

    None of the answers are correct.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!