Question: Process Improvement A local burger - making - delivery process is defined by the following model. Which change will deliver the most improvement in terms

Process Improvement
A local burger-making-delivery process is defined by the following model.
Which change will deliver the most improvement in terms of Process Cycle Time & Capacity?
Question 5 options:
Service the grill so Grill/Cook burgers takes 10 min.
Perform Divide and shape burger activity the night before.
Deploy a mobile app to drivers so Deliver meal takes only 8 min.
Improve Assemble burger cycle time by 75%.