Question: Process times for each step are in parenthesis and given in minutes per unit. A (8) B (96) (26) If a second worker was added

Process times for each step are in parenthesis
Process times for each step are in parenthesis and given in minutes per unit. A (8) B (96) (26) If a second worker was added to stage B, what is the new process bottleneck? None could be improved Stage A Stage C Stage B