Question: Processing time and due dates for five jobs is given below Job A B C D E Processing time (days) 7 35 50 7 14

Processing time and due dates for five jobs is given below

Job A B C D E
Processing time (days) 7 35 50 7 14
Due date (days) 122 50 86 48 41

If the jobs displayed in the table above are processed using the earliest-due-date rule,

a. What would be the lateness of job C? (Negative value should be indicated by a minus sign.)

b. What would be the lateness of job E? (Negative value should be indicated by a minus sign.)

c. What would be the tardiness of job D?

d. What is the maximum tardiness?

USE GIVEN VALUES