Question: Processing time and due dates for five jobs is given below Job A B C D AND Processing time (weeks) 1.5 2.5 2.0 1.0 2.0
Processing time and due dates for five jobs is given below
| Job | A | B | C | D | AND |
| Processing time (weeks) | 1.5 | 2.5 | 2.0 | 1.0 | 2.0 |
| Due date (weeks) | 6 | 7 | 8 | 3 | 6 |
If the jobs displayed in the table above are processed using the earliest-due-date rule,
a. What would be the lateness of job B? (Negative values should be indicated by a minus sign.)
b. What would be the tardiness of job E?
c. What is the maximum tardiness? (Round your final answer to 1 decimal place.)
d. What is the average flow time? (Round your final answer to 1 decimal place.)
USE GIVEN VALUES