Question: Processing Work i Deadline (d) time Pi 1 5 12 2 8 11 3 3 3 Suppose you are in charge of scheduling tasks in

Processing Work i Deadline (d) time Pi 1 5 12 2 8

Processing Work i Deadline (d) time Pi 1 5 12 2 8 11 3 3 3 Suppose you are in charge of scheduling tasks in a factory that makes bottles. 5 tasks must be programmed on a single machine. All jobs that need to be scheduled are available at this time, so the order release time is zero and you have been asked to minimize the maximum delay as a goal. 4 7 9 5 2 8 a) Calculate the maximum delay. Write your answer without decimals b) Calculate the total flow time