Question: PROCUREMENT AND CONTRACT MANAGEMENT (CALCULATION) PLEASE ANSWER ONLY IF YOU KNOW THE ANSWER AND CORRECTLY! Complete the empty fields in the following tables which compares

PROCUREMENT AND CONTRACT MANAGEMENT (CALCULATION)

PLEASE ANSWER ONLY IF YOU KNOW THE ANSWER AND CORRECTLY!

Complete the empty fields in the following tables which compares different contract types:

Table 1

Contract Type

Customer Payment

Actual Cost

Profit

Firm Fixed Price

Contracted (Target)

R400 000

R250 000

R150 000

Actual

R

R600 000

R

Actual

R

R150 000

R

Table 2

Contract Type

Customer Payment

Actual Cost

Fee

Cost plus fixed fee contract

Contracted (Target)

R7.25million

R7million

R

Actual

R

R8.75million

R

Actual

R

R4million

R

Table 3

Contract Type

Cost

Customer payment

Contractor Fee

??

Contracted (Target)

R

R5.75 million

R500 000

Contract with 60/40 sharing ratio and guaranteed maximum price (cost ceiling) of R6 million

Actual

R4million

R

R

Actual

R5.5million

R

R

Actual

R6.2million

R

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!