Question: Program Budget is $ 1 0 0 , 0 0 0 and the CPI is 0 . 8 . Program Manager attributes the variance to

Program Budget is $100,000 and the CPI is 0.8. Program Manager attributes the variance to faulty resource labor rates used by her predecessor, and predicts that variance will continue. If the actual cost till date is 23,000, what is the Estimate to Completion?
SELECT THE CORRECT ANSWER
$77,000
$1,02,000
$1,23,000
$1,03,000