Question: Project 1 and Project 2 have the cash-flows given in the table below. WACC = 15% Project Period project 1 project 2 0 -$50.00 -$100.00

Project 1 and Project 2 have the cash-flows given in the table below.

WACC = 15%
Project
Period project 1 project 2
0 -$50.00 -$100.00
1 $10.00 $10.00
2 $10.00 $20.00
3 $20.00 $30.00
4 $50.00 $40.00
5 $40.00
6 $40.00

What is the MIRR for project 1?

15.68%
16.08%
20.77%
18.21%
17.88%