Question: 1. Budget AT Completion (BAC)= $500 Estimate to Completion (ETC) = $400 Earned Value (EV) = $100 Actual Cost (AC) = $100 What is the
1. Budget AT Completion (BAC)= $500
Estimate to Completion (ETC) = $400
Earned Value (EV) = $100
Actual Cost (AC) = $100
What is the Estimate At completion (EAC)?
A) $0
B) $700
C) $800
D) $500
2. If the project has a CPI of 0.95, and SPI of 1.01, this indicates:
A) Project is progressing slower and costing more than planned
B) Project is progressing slower and costing less than planned
C) Project is progressing faster and costing more than planned
d) Project is progressing faster and costing less than planned
3.
Budget AT Completion (BAC)= $500
Estimate to Completion (ETC) = $400
Earned Value (EV) = $100
Actual Cost (AC) = $100
What is the Estimate At completion (EAC)?
A) $0
B) $100
C) $150
D) $500
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
