Question: Project 3 can be selected only if both Projects 1 and 2 are selected, but if both Projects 1 and 2 are selected, Project 3

Project 3 can be selected only if both Projects 1 and 2 are selected, but if both Projects 1 and 2 are selected, Project 3 doesn't have to be selected. The appropriate constraint would be
x3x1+x2
x1+x2x3
x1x3 and x2x3
x1+x2+x32
None of the above
 Project 3 can be selected only if both Projects 1 and