Question: Project A ends on March 8 , and you need to assign one staff member to Project B , which starts the first week of

Project A ends on March 8, and you need to assign one staff member to Project B, which starts the first week of Februar
\table[[Name,% time on Project A,\table[[% time committed],[to other tasks]],Notes],[Terry,40%,50%,Training - February 5],[Leon,30%,25%,Vacation - January 18 to 28],[Paul,80%,15%,Training - January 29 to 31],[Maria,100%,0%,In office],[Marco,20%,65%,Vacation - February 2 to 19]]
Which staff member should you choose?
Terry