Question: Project A ends on March 8 , and you need to assign one staff member to Project B , which starts the first week of

Project A ends on March 8, and you need to assign one staff member to Project B, which starts the first week of February.
\table[[,% Time on Project A,\table[[% Time Committed to Other],[Tasks]],Notes],[Name,Training - February 5,,],[Terry,40%,50%,Vacation - January 18 to 28],[Leon,30%,25%,Training - January 29 to 31],[Paul,80%,15%,In Office],[Maria,100%,0%,Vacation - February 2 to 19],[Marco,20%,65%,]]
Which staff member should you choose?
Terry
Leon
Paul
Maria