Question: Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to

Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the project manager?
Select one:
A. In this strong matrix, the balance of power is shifted to the project manager.
B. The project manager will probably not be challenged by project stakeholders.
C. In this tight matrix, the balance of power is shifted to the project manager
D. In this strong matrix, the balance of power is shifted to the functional line managers.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!