Question: Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to
Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the project manager?
Select one:
A In this strong matrix, the balance of power is shifted to the project manager.
B The project manager will probably not be challenged by project stakeholders.
C In this tight matrix, the balance of power is shifted to the project manager
D In this strong matrix, the balance of power is shifted to the functional line managers.