Question: Project A may yield a return of 3m with a probability of 0.3, or a return of 5m with a probability of 0.7. Project B
Project A may yield a return of 3m with a probability of 0.3, or a return of 5m with a probability of 0.7. Project B may earn a negative return of 3m with a probability of 0.3 or a positive return of 9m with a probability of 0.7. Compare the mean return and risk of the projects