Question: Project A Project B Initial Outlay (50,000) (70,000) Inflow Year 1 12,000 13,000 Inflow Year 2 12,000 13,000 Inflow Year 3 12,000 13,000 Inflow Year
| Project A | Project B | |
| Initial Outlay | (50,000) | (70,000) |
| Inflow Year 1 | 12,000 | 13,000 |
| Inflow Year 2 | 12,000 | 13,000 |
| Inflow Year 3 | 12,000 | 13,000 |
| Inflow Year 4 | 12,000 | 13,000 |
| Inflow Year 5 | 12,000 | 13,000 |
| Inflow Year 6 | 12,000 | 13,000 |
You are considering 2 independent projects, A and B. The required rate of return for both projects is 12%. Calculate NPV and indicate if the projects should be accepted.