Question: Project acceptance criteria include on - site training for the new users of a system. Due to unforeseen circumstances, all team members have to work

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.What should the project manager do?A. Reschedule on-site training to online sessions.B. Document the project issue and provide options.C. Create a risk and assign remediation actions.D. Cancel all of the on-site training sessions.