Question: Project B: What is / are the critical path ( s ) for this project? table [ [ Activity , Immediate Predecessor,Activity Duration ]

Project B: What is/are the critical path(s) for this project?
\table[[Activity,Immediate Predecessor,Activity Duration],[A,-,4],[B,-,2],[C,-,6],[D,A,B,2],[E,B,9],[F,D,E,5],[G,C,E,3],[H,G,F,9]]
 Project B: What is/are the critical path(s) for this project? \table[[Activity,Immediate