Question: Project Budget Task Date Budgeted Amount Build forms 1-Apr $10,000 Pour foundation 1-Apr $50,000 1-May $100,000 Frame walls 1-May $30,000 1-Jun $30,000 Remaining tasks July
| Project Budget | ||||||||
| Task | Date | Budgeted Amount | ||||||
| Build forms | 1-Apr | $10,000 | ||||||
| Pour foundation | 1-Apr | $50,000 | ||||||
| 1-May | $100,000 | |||||||
| Frame walls | 1-May | $30,000 | ||||||
| 1-Jun | $30,000 | |||||||
| Remaining tasks | July 1 and beyond | $500,000 | ||||||
| Budget at Completion (BAC) | ||||||||
| Results as of May 1 | ||||||||
| Foundation completed % | 66.67% | |||||||
| Everything else is on schedule. | ||||||||
| Actual Cost | $160,000 | |||||||
| Previous cost variances will not affect future costs | ||||||||
| Calculate as of May 1st | ||||||||
| PV | ||||||||
| EV | ||||||||
| AC | ||||||||
| SV | ||||||||
| CV | ||||||||
| SPI | ||||||||
| CPI | ||||||||
| ETC | ||||||||
| EAC | ||||||||
| Answer the following questions | ||||||||
| 1) Is the project on schedule as of May 1? What indicator did you use? Explain. | ||||||||
| 2) Is the project achieving more than predicted for the money as of May 1? What indicator did you use? Explain. | ||||||||
| 3) Is the project on budget as of May 1? What indicator did you use? Explain. | ||||||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock