Question: Project Charter Complete a Project Charter and any relevant RFP: *Project Charter Sponsor: Northern College Job: Newtomotive shop 3-bay garage Time: 5 months (20
Project Charter Complete a Project Charter and any relevant RFP: *Project Charter Sponsor: Northern College Job: Newtomotive shop 3-bay garage Time: 5 months (20 weeks) Internal Expertise: Engineer, Metal workers, Carpenters Needed Expertise: Electrician Price: $1,500,000 Expected Costs: $1,145,000 Time: 1 week level grou 2 weeks to pour and set foundation 3 weeks to install frame 2 weeks to complete exterior walls 3 weeks install vehicle lifts 3 weeks to install ramps -3 weeks complete electrical installation (lights and welding hook ups) 1 week install bay doors Slack time? Sponsor contact: Jason B. Start date: February 1st Approval: 1 week before start time