Question: Project Cost Data: Project duration is 9 months. Software licensing for a total cost of $ 6 0 , 0 0 0 ( a one

Project Cost Data:
Project duration is 9 months.
Software licensing for a total cost of $60,000(a one-time cost) is required during month 3.
System hardware installed on site is estimated to cost the firm $240,000 including shipment to the firms
location. The hardware must be unpacked, inspected, tested, and repacked at the firms location and then
shipped to the customer site at a cost of $6,000.
On-site hardware installation and testing will be subcontracted at a cost of $20,000. Installation should be done
no earlier than month 6, will require two weeks, and will be paid to the third party the month after it is
completed.
PM staff labor cost is $8,000 per month for the duration of the project.
Refinement and confirmation of system requirements (stretched evenly over months 1 and 2) will require 160
hours at the rate of $110/hour, plus two customer site visits at a cost of $2000 per trip.
Software development is expected to begin in month 2, span 5 months and require 3,000 hours of effort. The
labor rate for software developers is $130/hour.
Software testing will be conducted by a third party in month 7(some overlap with development is expected),
takes 5 weeks and will be paid when completed. The cost charged by the third party is $40,000.
On-site software installation and system testing (month 8) is expected to take three Full Time Equivalents (FTEs)
two full weeks each (5 workdays per week) including travel time. The labor rate for on-site installers/testers is
$80/hour and travel costs for the team is $4,000.
Training preparation (month 7) will require 95 hours at the rate of $100/hour.
On-site training delivery (month 9) will take 40 hours at a rate of $100/hour. Travel costs will not exceed $2,000.
Total project overhead, not including the PM staff labor cost, is an average of $10,000 per month.
$20,000 has been set aside each of the last 3 months as a reserve. Include this figure in your budget.
Markup any material costs and third-party fees by 20% in the cost baseline.
Hourly labor rates listed above are fully burdened.
This baseline or budget does not include the profit or other firm administrative costs

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!