Question: PROJECT CRASHING PROBLEM ( all time is Days, all cost in $ ) : What is the critical path? table [ [ Activity ,

PROJECT CRASHING PROBLEM (all time is Days, all cost in $): What is the critical path?
\table[[Activity,Immediate Predecessor,Normal Time,Crash Time,Normal Cost,Crash Cost],[A,-,5,4,1000,1400],[B,-,3,3,800,-],[C,A,B,3,1,600,900],[D,B,4,2,1600,2000],[E,C,D,5,3,800,1200],[F,E,2,1,1300,1400]]
ACDF
BCEF
BCDEF
BDEF
ACEF
 PROJECT CRASHING PROBLEM (all time is Days, all cost in $):