Question: Project Denali has three tasks. Task A has a PV of $2,500, is 85% complete, and actually cost $2,169 so far. Task B has a

 Project Denali has three tasks. Task A has a PV of

Project Denali has three tasks. Task A has a PV of $2,500, is 85% complete, and actually cost $2,169 so far. Task B has a PV $3,258 is 78% complete, and actually cost $3,030 so far. Task C has a PV of $2,875, is 90% complete, and actually cost $3,310 so far. The total budget is $8,788. 2. What is the Estimate at Completion (EAC) for the project? What is the Estimate to Completion for the project? What is the CPI for the project? What is the SPI for the project? a. b. d