Question: Project Denali has three tasks. Task A has a PV of $400, is 80% complete, and actually cost $395 so far. Task B has a

Project Denali has three tasks. Task A has a PV of $400, is 80% complete, and actually cost $395 so far. Task B has a PV $350, is 78% complete, and actually cost $330 so far. Task C has a PV of $275, is 92% complete, and actually cost $310 so far.

a. What is the Estimate to Completion for the project?

b. What is the CPI for the project?