Question: Project duration in calendar days is D . 1 9 A . 1 7 B . 1 4 C . 2 0 The critical path

Project duration in calendar days is
D.19
A.17
B.14
C.20
The critical path is
A. A-B-E-F
B.A-B-D
C. A-C-E-F
D.A-C-D
The free float of activity F in working days is
A. Zero
B.1
C.2
D.3
The activity with Free Float =0 but Total Float 0 is
A. Activity C
B. Activity D
C. Activity E
D. Activity F
The total float for activity C in working days is
A. Zero
B.3
C.4
D.7
If the last Saturday (Oct.19) is converted into a working day, the project will be completed on
A. October 19
B. October 18
C. October 17
D. None of the above
A reviewer of the above-shown bar chart schedule suggests changing the duration of activity E to 5 days. If this change is implemented, the total float of activity F will become
A. Zero
B.1
C.2
D.3
With reference to the previous question (if the duration of activity E is changed to 5 days), the only activity with non-zero float would be
A. Activity F
B. Activity D
C. Activity E
D. Activity C
Project duration in calendar days is D . 1 9 A .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!