Question: Project estimate information is provided as follows: Optimistic cost = $900 Most likely cost =$1000 Pessimistic cost = $2100 Use the Rule of 6, PERT

Project estimate information is provided as follows:

  • Optimistic cost = $900
  • Most likely cost =$1000
  • Pessimistic cost = $2100

Use the Rule of 6, PERT to calculate the best estimate based on the above information

$1000

$1333

$1167

$2333

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!