Question: PROJECT EVALUATION AND REVIEW TECHNIQUE ( PERT ) Q 4 . Page 1 0 2 q 8 The following represents a project that should be

PROJECT EVALUATION AND REVIEW TECHNIQUE (PERT)
Q4. Page 102 q8
The following represents a project that should be scheduled using CPM:
Time estimate (days)
Activity
Activity predecessor
a
m
b
A
-
1
3
5
B
-
1
2
3
C
A
1
2
3
D
A
2
3
4
E
B
3
4
11
F
C, D
3
4
5
G
D, E
1
4
6
H
F, G
2
4
3
a. Draw the network
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!