Question: Project information for a company's tailor-made project is presented below. Use the Critical Path method to find out the duration of the project. Calculate the
Project information for a company's tailor-made project is presented below. Use the Critical Path method to find out the duration of the project. Calculate the early and late times of the activities, as well as the slack times, and identify the critical path. Additionally answer the following questions:
a) What if the duration of a critical activity is increased?
b) What would happen if the duration of a non-critical activity is decreased?
| ID | ACTIVITY | PREDECESSOR | TIME |
| A | REQUEST REVIEW | None | 2 |
| B | ORDER STANDARD PARTS | A | 15 |
| C | Produce standard parts | A | 10 |
| D | Design custom parts | A | 13 |
| E | Develop software | A | 18 |
| F | Design custom software | C,D | 15 |
| G | Assemble | B,F | 10 |
| H | Try | E,G | 5 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock