Question: project It we hire the designer . What will be the new probability of finishing the project within 19 weeks ( 133 days ) ?

 project It we hire the designer . What will be the

project It we hire the designer . What will be the new probability of finishing the project within 19 weeks ( 133 days ) ? Hint : This change could potentially change your critical path , so please check that before* you calculate the new project completion time . h ) What is the most Smartoffice " should be willing to pay the outside designer who could finish Activity Cin exactly four days ?&quot