Question: Project Management 10 50 1 - 10 days A-25 days D-10 days F-15 days Start B-5 days 20 E - 15 days 40 G-10 days

Project Management 10 50 1 - 10 days A-25 days D-10 days F-15 days Start B-5 days 20 E - 15 days 40 G-10 days 60 J-5 days End C-20 days H-20 days 30 a. b. What is the name of the above diagram? Begin with 'Start", identify the critical path. Assuming the project proceeded according to the schedule, how long does it take to complete the whole project? What is the slack time for activity G without affecting the project schedule? C. d