Question: Project Management: 1.a. An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of
Project Management:
1.a. An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected standard deviation of the activity? A) between 2 and 3 days B) between 3 and 4 days C) between 4 and 5 days D) between 5 and 6 days
Show calculation
1b. What is the float start time for Activity C given the activity times and precedence requirements shown in the table? Show work
| Activity | Time | Predecessor |
| A | 5 | -- |
| B | 8 | A |
| C | 4 | A |
| D | 5 | B, C |
A) 1
B) 2
C) 3
D) 4