Question: Project Management: 1.a. An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of

Project Management:

1.a. An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected standard deviation of the activity? A) between 2 and 3 days B) between 3 and 4 days C) between 4 and 5 days D) between 5 and 6 days

Show calculation

1b. What is the float start time for Activity C given the activity times and precedence requirements shown in the table? Show work

Activity Time Predecessor
A 5 --
B 8 A
C 4 A
D 5 B, C

A) 1

B) 2

C) 3

D) 4