Question: Project Management 1.prepare budget with listing down all work packages and activities. create total budget on first Excel Sheet and time faced budget on 2nd
Project Management

1.prepare budget with listing down all work packages and activities. create total budget on first Excel Sheet and time faced budget on 2nd sheet of Excel.
Activity Task Preceding Activity None Activity Time (Work Weeks) 1 2 None 10 3 Connecting Software Project for Mrs. Y Requirement Collection Resource Allocation Hardware Specification Software Build 2 4 4 2 4 5 3 10 6 4 2 7 3,9 1 8 6 2 Unit Testing IPR Filing System Testing End to End Testing Project Handover END (Milestone) 9 5 5 10 7,9 4 11 10 0 Customized Connecting Software Requirement Collection Resource Allocation Hardware and Software Built End of Testing Project HandoverStep by Step Solution