Question: Project management (2) Durations (weeks) 6 3 Consider the following project: Activity Immediate Predecessors A B A A D B E F B,C G DE

Project management (2) Durations (weeks) 6 3

Project management (2) Durations (weeks) 6 3 Consider the following project: Activity Immediate Predecessors A B A A D B E F B,C G DE H 2 3 8 3 7 2 Which activity is not a critical activity? Multiple Choice . E OC