Question: Project management and value engineering The duration of Activity A-4 Days, The total cost of Activity A = 4000 JD The duration of Activity B=2
Project management and value engineering

The duration of Activity A-4 Days, The total cost of Activity A = 4000 JD The duration of Activity B=2 Days, The total cost of Activity B - 13000 JD The duration of Activity C=5 Days, The total cost of Activity C = 14000 JD The duration of Activity D=6 Days, The total cost of Activity D = 10000 JD The duration of Activity E-4 Days, The total cost of Activity E - 16000 JD Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Activity B c D E Cost (JD) Calculate the project cost on Day#3 B