Question: PROJECT MANAGEMENT course 1. Jane is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this

PROJECT MANAGEMENT course
1. Jane is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project. She calculated early and late start times and early and late finish times but spilled coffee all over her printout. Use the remaining information to reconstruct the table for Jane and her new canoe canal. Immediate Predecessor(s) Early Finish 12 Late Finish Length Early Start Late Start 20 Activity A B D E F G H 42 42 50 A A B, E E D G G F H, I, J 28 42 53 70 53 72 I J 4 K 81 91Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock