Question: Project Management Example 1 CPM with Single Time Estimates Use this simple project information to answer the following questions: Task Estimated Duration Immediate Predecessors A

Project Management Example 1
CPM with Single Time Estimates
Use this simple project information to answer the following questions:
Task Estimated Duration Immediate Predecessors
A 10 days None
B 7 days A
C 4 days A
D 8 days B, C
1. What are the paths to complete this project?
2. What is the project duration?
3. What is the critical path for this project?
4. What is the earliest start time for activity C?
5. What is the latest start time for activity C?
6. Which activity(ies) has (have) slack and how much slack does it (do they) have?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!