Question: Project Management Help Save & Exit Submit Problem 5 - 5 ( Algo ) oints Your project to obtain charitable donations is now 3 1
Project Management
Help
Save & Exit
Submit
Problem Algo
oints
Your project to obtain charitable donations is now days into a planned day project. The project is divided into activities. The first activity is designed to solicit individual donations. It is scheduled to run the first days of the project and to bring in $ Even though we are days into the project, we still see that we have only percent of this activity complete. The second activity relates to company donations and is scheduled to run for days starting on day and extending through day We estimate that, even though we should have percent of this activity complete, it is actually only percent complete. This part of the project was scheduled to bring in $ in donations. The final activity is for matching funds. This activity is scheduled to run the last days of the project and has not started. It is scheduled to bring in an additional $ So far $ has actually been brought in on the project.
Print
Calculate the schedule variance, schedule performance index, cost variance, and cos actually value in this case performance index.
Note: Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to decimal places.
tableSchedule variance,Schedule performance index,Cost variance,Cost performance index,
Prev
of
Next
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock