Question: Project Management If the project has a negative cost variance, then a. no action is needed to be taken, the project is performing well. b.
Project Management
If the project has a negative cost variance, then
a. no action is needed to be taken, the project is performing well.
b. the project should be watched to be sure the project progresses.
c. more money needs to be expended on the project
d. correction actions should be taken on activities that are near-term and have large estimated costs.